git init -q -b main
kanbanr init shop --data-dir <tmp>/shop-board --author Ada --email ada@example.com
kanbanr config workflow --preset agile
kanbanr config cadence --git-model on
kanbanr git install-hooks
workflow updated
sprints on, releases on, estimates in days, git model on
installed commit-msg and pre-commit and pre-push in <tmp>/shop: a commit now has to say which item it serves
The agile preset already turns sprints and releases on. kanbanr git model shows what the git model
will do. Nothing is pushed for you:
topology: sprints and releases
main: main
line: none — start a sprint to have one
branch at: sprint/<SP>
production: at the release cut
items: feat/{code}-{slug}, fix/{code}-{slug}, spike/*
protected: main, sprint/*, release/*
kanbanr merges:
- each item branch into sprint/<SP> when the item enters the integrate stage (--no-ff, naming the item)
- release/<V> into main at the release's last stage (tagged <V>, a fast-forward)
- sprint/<SP> into each item branch carried into that sprint (a catch-up merge; a conflict is reported for that item)
pushing: never automatic — you review and push
automation: on — start, sprints and the hooks follow this model
Then agree the charter before creating items. Without one, moves that should be refused still
succeed, but each says what the gate would have needed and that kanbanr charter set turns the
gates on:
kanbanr charter set --file charter.yaml
Release stages
A project that turns releases on gets three stages, candidate, main and tag, with their gates
written into the board’s config, so you can see and edit them. Main has to be pushed before
anything is tagged. Candidate waits for items_merged, so the release branch is made only once the items are
merged; the commands below set the same thing. kanbanr can’t see whether CI passed. Look at your CI yourself, then record what it
said with kanbanr gate record ci --passed --url <link to the run>. Say the project has CI with
kanbanr config cadence --has-ci on and the tag stage requires that result
(Gate results); without the flag it requires only
main_at_release and pushed.
A board made before 0.6 that has releases on and names no stages keeps the four it had,
candidate, test, staging and production. test and staging do nothing, and kanbanr says so
when you configure them and in kanbanr release stages. To move such a board to the three, run
kanbanr config cadence --release-stages candidate,main,tag, then the release-stage lines below.
Stages you add after tag follow the cut and are confirmed by you.
kanbanr config cadence --release-stages candidate,main,tag
kanbanr config release-stage candidate --requires items_merged --on-enter branch,prepare
kanbanr config release-stage main --requires items_finished --on-enter move_main
kanbanr config release-stage tag --requires main_at_release,pushed --on-enter tag
kanbanr config release-prepare --version-file package.json --changelog CHANGELOG.md --notes "docs/releases/{version}.md"
STAGE REQUIRES ON ENTER
candidate items_merged branch, prepare
main items_finished move_main
tag main_at_release, pushed tag the cut
To stop a release being promoted while work is still going on, have the candidate stage require
items_merged: every item planned into the release must be at the integrate stage or later (for
TOGAF, Migration), and the plan names each item that is not, with the status it is at. And to stop a
named promotion jumping over a stage, list it in --after: kanbanr then refuses to enter the stage
until the release has been promoted into the one named. For example, with a ci stage you record
yourself:
kanbanr config cadence --release-stages candidate,main,ci,tag
kanbanr config release-stage tag --after ci
kanbanr records that the stage was entered, not that CI passed. To require a recorded CI result as
well, use gate_passed.
Planning a sprint
Setup creates no sprint or release; make them when you are ready. A sprint can be changed until it
starts (kanbanr sprint edit SP-001 --goal "…" --start 2026-11-10), and an empty sprint or release
made by mistake is removed with kanbanr sprint remove SP-001 or kanbanr release remove v1.0.0.
kanbanr milestone add --name "Carts"
kanbanr sprint add --start 2026-11-03 --length 2w --goal "Carts survive a return"
# or start it today: kanbanr sprint add --start today --length 2w --goal "…"
kanbanr sprint start SP-001
kanbanr feature add --title "Restore the cart" --milestone MS-001 --spec "# Restore the cart"
kanbanr sprint plan SP-001 FEAT-001
kanbanr sprint unplan FEAT-001 # take it back out
kanbanr release add v1.0.0
kanbanr release plan v1.0.0 FEAT-001
created milestone MS-001
added SP-001 (2026-11-03 → 2026-11-16)
SP-001 is the active sprint; created sprint/SP-001 from main
created FEAT-001 (Plan)
planned FEAT-001 into SP-001 (0 committed)
added release v1.0.0
planned FEAT-001 into v1.0.0
One item, stage by stage
Each move is refused until its gate is met, and the refusal says what’s missing. kanbanr check shows
it before you try.
| Stage | What must be true to enter | Commands |
|---|---|---|
| Plan | Nothing | kanbanr feature add |
| Design | Statement, goals, requirements, approval | kanbanr feature define, kanbanr approve |
| Develop | How and where, a test named for every requirement, the design-review sign-off | kanbanr feature edit, kanbanr signoff, kanbanr start |
| Test | Nothing | kanbanr move |
| Review | Requirements proven by green tests, the docs-folded sign-off | kanbanr test, kanbanr signoff, kanbanr move |
| Released | In a release; the cut does the move | kanbanr release promote |
Moving to Design with no definition:
$ kanbanr move FEAT-001 "Design"
error: unsupported operation: cannot move FEAT-001 to 'Design': no definition — why it exists, what must be true, how it is verified (`kanbanr feature define`). To proceed anyway, record why with --override "<reason>"
Define it, then write the spec. The move is still refused until you approve:
$ kanbanr feature define FEAT-001 --file definition.yaml
defined FEAT-001: 1 requirement(s)
$ kanbanr feature edit FEAT-001 --spec-file spec.md
updated FEAT-001
$ kanbanr move FEAT-001 "Design"
error: unsupported operation: cannot move FEAT-001 to 'Design': not approved. To proceed anyway, record why with --override "<reason>"
$ kanbanr approve FEAT-001
FEAT-001 approved by Ada
$ kanbanr move FEAT-001 "Design"
FEAT-001 -> Design
Code starts at Develop. kanbanr start makes the item’s branch from the sprint’s branch. Without
the design-review sign-off it says what’s missing and makes no branch:
$ kanbanr start FEAT-001 --to "Develop"
error: unsupported operation: cannot move FEAT-001 to 'Develop': no sign-off 'design-review' — `kanbanr signoff FEAT-001 design-review`. To proceed anyway, record why with --override "<reason>"
$ kanbanr signoff FEAT-001 design-review
FEAT-001: sign-off 'design-review' recorded by Ada
$ kanbanr start FEAT-001 --to "Develop"
created feat/FEAT-001-restore-the-cart from sprint/SP-001
FEAT-001 -> Develop
Commit with kanbanr commit, then move to Test:
$ kanbanr commit -m "feat: restore the cart"
[feat/FEAT-001-restore-the-cart 74aa8cc] feat: restore the cart
1 file changed, 1 insertion(+)
create mode 100644 cart.txt
$ kanbanr move FEAT-001 "Test"
FEAT-001 -> Test
Review is where the merge happens. It needs green tests and the docs-folded sign-off:
$ kanbanr move FEAT-001 "Review"
error: unsupported operation: cannot move FEAT-001 to 'Review': R-1 has tests but none is green — not yet proven; no sign-off 'docs-folded' — `kanbanr signoff FEAT-001 docs-folded`. To proceed anyway, record why with --override "<reason>"
$ kanbanr test FEAT-001 R-1 "cart_restores_after_return" green --rev 74aa8cc83c09aa4eef7b0d856da1efbfa605609c
FEAT-001/R-1 · cart_restores_after_return -> green
$ kanbanr signoff FEAT-001 docs-folded
FEAT-001: sign-off 'docs-folded' recorded by Ada
$ kanbanr move FEAT-001 "Review"
FEAT-001 -> Review
merged feat/FEAT-001-restore-the-cart into sprint/SP-001 (fe92a82b0741)
Now kanbanr check says the item is ready for Released:
✓ FEAT-001 Restore the cart
→ Released (Shipped in a release.): ready to move on
Your checkout stays on the item’s branch, so switch back when you want the sprint’s line. A move can
also go past its gate with --override "<reason>", and the reason stays on the item. Save it for real
exceptions.
Chores
A process can give a kind its own path. The built-in agile process gives chore the path
Plan → Develop → Test → Review → Released, skipping Design. A chore passes Review, where its branch merges, so it is in the line before a release is cut. kanbanr process show agile lists each kind’s path under
“Lighter paths”.
kanbanr feature add --title "Pin the CI image" --milestone MS-001 --kind chore
A chore’s first move off Plan asks the path’s own conditions (statement, goals,
requirements, and ears where the path lists it) as well as the entered stage’s gate, so it still
records why it exists and how it is verified. A move to a stage off the path is refused, and the
message names the path. The entered stage’s gate still applies, approved included; the design and design-review parts do not apply. An item whose kind is changed to chore while it’s at a
stage off the path keeps the ordinary transitions, so it is never stranded.
Releasing
Before your first release, design the pipeline. A release workflow can only be tested by running it, a tag can’t be moved once it’s pushed, and shipped notes can’t be edited, so a mistake in the pipeline costs a whole version number. Settle the stages, the checks, the release description and a run without a tag first: see Designing CI and the release workflow.
kanbanr release promote v1.0.0 --plan shows what a promotion would do and changes nothing.
v1.0.0: Promote to candidate (— → candidate)
does:
→ branch (candidate): makes release/v1.0.0 from sprint/SP-001
→ prepare (candidate): commits the version 1.0.0, the changelog heading and draft notes to release/v1.0.0
ready: `kanbanr release promote v1.0.0 candidate`
after: then Promote to main
(a plan: nothing was changed)
| Step | Command | What happens |
|---|---|---|
| 1. Candidate | kanbanr release promote v1.0.0 candidate | Makes release/v1.0.0 from the sprint’s branch, and commits the version, the changelog heading and draft notes onto it |
| 2. Read the notes | kanbanr release notes v1.0.0 | The draft only lists requirements. Rewrite it with --edit |
| 3. Run your full checks | Your project’s own | Over the release |
| 4. Main | kanbanr release promote v1.0.0 main | Fast-forwards main to the release, without tagging |
| 5. Push main | git push origin main | |
| 6. Wait for CI, then record it | kanbanr gate record ci --passed --url <link to the run> | Once CI on main is green. The cut waits for it |
| 7. Cut | kanbanr release promote v1.0.0 tag | Tags main, ships the items and moves them to Released |
| 8. Push the tag | git push origin v1.0.0 | |
| 9. Merge forward | kanbanr git forward v1.0.0 | Brings the release’s commits into the sprint’s branch |
The candidate:
v1.0.0 -> candidate; created release/v1.0.0
makes release/v1.0.0 from sprint/SP-001
commits the version 1.0.0, the changelog heading and draft notes to release/v1.0.0
prepared 59e2014e8aae on release/v1.0.0
next: `kanbanr release promote v1.0.0` (Promote to main)
The draft notes:
release/v1.0.0 @ 59e2014: docs/releases/v1.0.0.md
# v1.0.0
_Released 2026-11-04._
A patch release starts at **candidate** the moment it is created, so there is no first stage to promote from. Claude asks you in the conversation to confirm it; main and the tag are then decided on the Releases page as usual. `kanbanr release add v1.0.1 --patch-of v1.0.0` creates it at candidate.
## What shipped
#### Stages after the tag
The stage that tags is the cut, but it does not have to be the last. Add stages after it, for the
places you run the release before it counts as out, and each becomes a confirmation you give:
```text
kanbanr config cadence --release-stages candidate,main,tag,staging,production
kanbanr config release-stage tag --on-enter tag
kanbanr config commit-gates ci
Promoting to tag tags the commit and ships nothing. The Releases page then shows the result you
recorded for the tag and asks for the next stage only after a passed one. Each stage after the
tag, staging and production here, is confirmed with
kanbanr release promote <VERSION> --note "what you checked". Confirming the last stage ships the
release: the items reach their last status and the notes are written. If your CI fails on the tag,
record the failed result and run kanbanr release add <NEW VERSION> --patch-of <VERSION> --from-failed-tag --link <run> --notes "what you saw": it files a defect with the link and your
notes, plans it and the release’s items into a patch branched from the tag, and marks the failed
release as superseded. The tag stays in git.
FEAT-001 — Restore the cart
A returning shopper finds their cart for shoppers so that they don’t lose it
- WHEN a shopper returns, THE SYSTEM SHALL restore their cart
Main:
```text
v1.0.0 -> main; main fast-forwarded to it, not tagged
fast-forwards main to release/v1.0.0 (59e2014)
next, for Claude: bring release/v1.0.0 into sprint/SP-001 with `kanbanr git forward v1.0.0` — a local merge, nothing is pushed; a conflict stops it with nothing changed
59e2014e8aae Release v1.0.0: version, changelog and notes
nothing was pushed: push main when you are ready
next: push main (`git push origin main`), then wait for CI, then Cut v1.0.0
$ git push origin main
To <tmp>/origin.git
c699fc1..59e2014 main -> main
The cut, then the tag push and the merge forward:
v1.0.0 -> tag; tagged v1.0.0, where main already is
tags 59e2014 "Release v1.0.0" as v1.0.0
shipped 1 item(s); notes in releases/v1.0.0.md
next, for Claude: bring release/v1.0.0 into sprint/SP-001 with `kanbanr git forward v1.0.0` — a local merge, nothing is pushed; a conflict stops it with nothing changed
59e2014e8aae Release v1.0.0: version, changelog and notes
nothing was pushed: push the tag when you are ready
push the tag: `git push origin v1.0.0`
$ git push origin v1.0.0
To <tmp>/origin.git
* [new tag] v1.0.0 -> v1.0.0
$ kanbanr git forward v1.0.0
merged release/v1.0.0 forward into sprint/SP-001 (a76f622b0e74)
The item and the release now read:
$ kanbanr release list
v1.0.0 shipped tag target — 1 item(s)
Freeze the candidate. Once a release is a candidate, send anything new to the next release and
change only its notes. Promoting moves main, not your checkout. The date follows the release:
promoting to main dates the notes and changelog today. If main moved earlier and the cut comes
later, the cut’s --plan warns, and kanbanr release redate v1.0.0 dates them today.
Feedback on a release
Feedback is a new item that names the version it was found in:
kanbanr feature add --title "…" --milestone MS-001 --found-in v1.0.0
(I did not run this in the walkthrough.) For a fix to a shipped release, see Patch releases.
Closing the sprint
$ kanbanr sprint close SP-001
closed SP-001; nothing carried over
look back on it: `kanbanr retro --sprint SP-001`
Closing changes the board only. Start the next sprint before starting any item, because new items
branch from the running sprint. After the cut, kanbanr doctor suggests deleting the merged item
branch with git branch -d feat/FEAT-001-restore-the-cart.
When things go wrong
| You see | It means | Do this |
|---|---|---|
no definition | The item has no definition | kanbanr feature define |
not approved | The definition isn’t approved, or changed since | kanbanr approve |
no sign-off 'design-review' on start | The branch was made, but the item stayed in Design | Sign off, then run kanbanr start again |
R-1 has tests but none is green | A requirement isn’t proven | kanbanr test with the result |
no sign-off 'docs-folded' | The docs step isn’t signed off | kanbanr signoff FEAT-001 docs-folded |
| A defect in a shipped release | It needs a fix on its own | See Patch releases |
See also the guides index.